Sizing and Selecting a Transformer
Sizing and Selecting a Transformer
· Transformer size is determined by the kVA of the load.
· Load voltage, or secondary voltage, is the voltage needed to
operate the load.
· Line voltage, or primary voltage, is the voltage from the source.
· Single-Phase has two lines of AC power.
· Three-Phase has three lines of AC power, with each line 120
degrees out of phase with the other two.
· KVA is kilovolt ampere or thousand volt ampere. This is how
transformers are rated.
To determine the size of the transformer you need, determine the
following requirements for your transformer:
1. Load Voltage
2. Load Current/Amps
3. Line Voltage
Next, determine if your application is single-phase or
three-phase, and use the corresponding formula at the right.
The KVA of the transformer should be equal to or greater than the KVA
of the load to handle present requirements and to account for future expansion.
As a service to you, we offer a transformer specifier to help you find your
transformers quickly and easily.
Installation
Carefully inspect the transformer before signing the delivery
receipt. Any damage should be noted on the receipt and a claim placed against
the transportation company. Protective greaseplaced on terminal connections
should not be removed. The grease is a protective coating that prevents the
oxidation of the conductor. Bolt the terminal connector firmly to the bus bar,
allowing the protective film to be forced out.
Safety
Transformers are provided with access covers to facilitate
installation and service. They must be kept securely in place at all times when
the transformer is operating.
CAUTION: Normal operating voltages can be extremely hazardous.
Only qualified personnel should install, inspect or service transformers.
Disconnect the power before opening the cover or touching any internal parts.
Storage
Transformers should be stored in a warm, dry location of uniform
temperature and in their original packing. If the transformer has been unpacked,
all ventilating openings should be covered to keep out dust. Outdoor storage
should be avoided, but if this is not possible, the transformer must be
protected against moisture and contaminants.
Condensation and moisture can be reduced with heaters. If the
transformer has been subjected to moisture, it should be baked out before
energizing. This is especially important in transformers of 5 KV or higher.
Taps
If the transformer comes supplied with taps, they will generally
have a full capacity rating. A common tap arrangement is two 2.5% taps above
(FCAN) and four 2.5% taps below (FCBN) nominal voltage. Transformers are
shipped with the taps connected for nominal voltage, that is, 480 volts for a
480 volt transformer. The installing electrician must change the taps if the
supply voltage differs from the nominal voltage rating.
Connections and Circuits
The transformer should be connected only as described on the
nameplate or the wiring diagram inside the wiring compartment cover, or as
otherwise specifically authorized by Jefferson Electric. Transformers without
terminal boards, usually the smaller size transformers, provide leads for
connections.
IMPORTANT: Any unused taps or leads must be insulated from each
other and taped encapsulated transformers, 2 KVA and smaller, have their turns
ratio compensated for losses so that their open circuit voltage is somewhat
higher than the load voltage. Machine tool transformers are compensated up to 5
KVA. Using transformers in the reverse direction from which it is designed
would result in lower than expected output voltage.
Mounting and Spacing
Dry-type transformers depend on air for cooling, and must be
placed so that room air can circulate freely around them. Cabinet style
transformers must be mounted so that air can pass freely through the
ventilation openings. The transformer space should be kept clear.
Transformers should be spaced at least six inches apart.
Transformers rated 30 KVA and larger should be kept at least six inches from
walls and ceilings.
Transformers should never be mounted near heat-generating
equipment or near heat-sensitive equipment. Transformers should never be placed
in a room with hazardous processes, or where flammable gasses or combustible
materials are present. Particular care must be taken when mounting in
unventilated plenums or in closets with no ventilation. In areas without free
moving air, ambient temperatures can rise above acceptable limits, causing the
transformer to overheat.
Maintenance
Periodic inspection of the transformer should be made, depending
on conditions. In most clean, dry installations, once a year is usually
sufficient. After disconnecting the transformer from the power, the cover
should be removed and any dirt cleaned out. Screens covering the ventilating openings
should be cleaned.
Inspect for loose connections, terminal and splice conditions and
for signs of overheating, rust or deteriorating paint.
NEMA Transformer Enclosure Definitions
|
|
Type 1
|
General purpose
- indoor.
|
Type 2
|
Drip-proof -
indoor.
|
Type 3
|
Wind blown dust
and water - indoor/outdoor.
|
Type 3R
|
Rainproof and
sleet/ice resistant - outdoor. Meets above type requirements.
|
Type 3S
|
Dust-tight,
rain-tight, and sleet/ice proof - outdoor.
|
Type 4
|
Water-tight and
dust-tight - indoor/outdoor.
|
Type 4X
|
Water-tight,
dust-tight and corrosion resistant - indoor.
|
Type 5
|
Dust-tight -
indoor.
|
Type 6
|
Submersible,
water-tight, dust-tight and sleet/ice resistant - indoor/outdoor.
|
Type 7
|
Class I, Group
(S) A,B,C and/or D - indoor hazardous locations - air-break equipment.
|
Type 8
|
Class I, Group
(S) A,B,C and/or D - indoor hazardous locations.
|
Type 9
|
Class II, Group
(S) E,F and/or D - indoor hazardous locations - air-break equipment.
|
Type 10
|
Bureau of
Mines.
|
Type 11
|
Drip-proof and
corrosion resistant.
|
Type 12
|
Industrial use
dust-tight and drip-tight - indoor.
|
Type 13
|
Oil-tight and
dust-tight - indoor.
|
Source: NEMA Pub. No. ST20.
|
Recommended Copper Wire & Transformer Size
|
||||||
Single-Phase Motors - 230 Volts
|
||||||
HP
|
Transformer KVA
|
Distance - Motor to Transformer in Feet
|
||||
100
|
150
|
200
|
300
|
500
|
||
11/2
|
3
|
10
|
8
|
8
|
6
|
4
|
2
|
3
|
10
|
8
|
8
|
6
|
4
|
3
|
5
|
8
|
8
|
6
|
4
|
2
|
5
|
71/2
|
6
|
4
|
4
|
2
|
0
|
71/2
|
10
|
6
|
4
|
3
|
1
|
0
|
Source: EASA Handbook
|
Recommended Copper Wire & Transformer Size
|
|||||||
Three-Phase Motors -230 & 460 Volts
|
|||||||
HP
|
Volts
|
Transformer KVA
|
Distance - Motor to Transformer in Feet
|
||||
100
|
150
|
200
|
300
|
500
|
|||
11/2
|
230
|
3
|
12
|
12
|
12
|
12
|
10
|
11/2
|
460
|
3
|
12
|
12
|
12
|
12
|
12
|
2
|
230
|
3
|
12
|
12
|
12
|
10
|
8
|
2
|
460
|
3
|
12
|
12
|
12
|
12
|
12
|
3
|
230
|
5
|
12
|
10
|
10
|
8
|
6
|
3
|
460
|
5
|
12
|
12
|
12
|
12
|
10
|
5
|
230
|
71/2
|
10
|
8
|
8
|
6
|
4
|
5
|
460
|
71/2
|
12
|
12
|
12
|
10
|
8
|
71/2
|
230
|
10
|
8
|
6
|
6
|
4
|
2
|
71/2
|
460
|
10
|
12
|
12
|
12
|
10
|
8
|
10
|
230
|
15
|
6
|
4
|
4
|
4
|
1
|
10
|
460
|
15
|
12
|
12
|
12
|
10
|
8
|
15
|
230
|
20
|
4
|
4
|
4
|
2
|
0
|
15
|
460
|
20
|
12
|
10
|
10
|
8
|
6
|
20
|
230
|
*
|
4
|
2
|
2
|
1
|
000
|
20
|
460
|
*
|
10
|
8
|
8
|
6
|
4
|
25
|
230
|
*
|
2
|
2
|
2
|
0
|
000
|
25
|
460
|
*
|
8
|
8
|
6
|
6
|
4
|
30
|
230
|
*
|
2
|
1
|
1
|
00
|
0000
|
30
|
460
|
*
|
8
|
6
|
6
|
4
|
2
|
40
|
230
|
*
|
1
|
0
|
00
|
0000
|
300
|
40
|
460
|
*
|
6
|
6
|
4
|
2
|
0
|
50
|
230
|
*
|
1
|
0
|
00
|
0000
|
300
|
50
|
460
|
*
|
4
|
4
|
2
|
2
|
0
|
60
|
230
|
*
|
1
|
00
|
000
|
250
|
500
|
60
|
460
|
*
|
4
|
2
|
2
|
0
|
00
|
75
|
230
|
*
|
0
|
000
|
0000
|
300
|
500
|
75
|
460
|
*
|
4
|
2
|
0
|
00
|
000
|
* Consult Local
Power Company
Source: EASA Handbook |
Protective Equipment
The importance of protecting your power delivery system cannot be
overstated. The system must be protected against short circuits, surges caused
by lightning, switching and overheating. Equipment is available to provide this
protection, but it must also be adequately sized and properly installed.
Failure to do so could damage the transformer and invalidate its warranty.
Protective equipment includes circuit breakers and fuses.
The selection and placement of protective equipment within the
system is the responsibility of the end user.
Circuit Breakers
When any component of a circuit fails, there is nothing to limit
current flow except the resistance of the circuit conductors and the resistance
of the fault itself. The currents in these situations can be extremely large
and destructive, making it imperative to interrupt the circuit as quickly as
possible.
Circuit breakers are designed to react to a fault by making a
physical separation in the currentcarrying or conducting element by inserting
an insulating medium. Breakers come in different types, depending on the
insulating medium used. While the most common insulation is oil, air is used in
some 600 Volt class circuits. For higher voltages and larger capacities, the
insulating medium might be a vacuum or and inert gas such as sulphur
hexafluoride.
Specifications for a circuit breaker will depend on the operating
voltage of the circuit, the normal operating or maximum load current, and the
maximum abnormal or fault current to be interrupted. Circuit breakers are rated
in KVA or MVA and express the ability of the breaker to withstand short circuit
forces.
Circuit breakers must withstand large inrush currents that result
when voltage is initially switched on. These currents can be 20 to 30 times the
rated transformer current even with no-load. Therefore, breakers must have
built-in time delay for the first 5 to 10 cycles to avoid tripping under
"turn-on" currents.
Fuses
The most common protective device in use, the fuse is basically a
circuit breaker that works only once and then must be replaced. When current
exceeds the predetermined current value, a fusible link melts, opening the
circuit. When voltage is initially switched on, a large inrush current results,
being greatest in the first half-cycle of operation, or approximately .01
second. This current becomes less severe over the next few cycles, or
approximately .1 second until the transformer is operating normally. Because of
inrush current, fuses are often selected to withstand as much as 25 times
primary rated current for .01 second, and 12 times primary rated current for .1
second.
Fuse Selection
The tables provide guidance for selecting fuses when the maximum
voltage in the circuit is 600 Volts or less. These tables are included in
Article 450-3 of the National Electrical Code covering over-current protection
of transformers. If primary protection only is required, use Table 1. If both
primary and secondary protection are required, refer to Table 2.
IMPORTANT: These tables are to be used as a guide only. The final
determination of application is the responsibility of the end user.
Table 1 - Primary Fuse Only
|
|
Transformer Primary Amperes
|
Maximum Primary Fuse % Rating
|
9 or More
|
125*
|
2 or 9
|
167
|
Less than 2
|
300
|
* If 125% does
not correspond to a standard ampere rating, the next higher standard rating
described in NEC Article 240-6 shall be permitted.
|
Table 2 - Primary and Secondary Fuses
|
||
Transformer Secondary Amperes
|
Maximum % Rating
|
|
Primary Fuse
|
Secondary Fuse
|
|
9 or More
|
250
|
125*
|
Less than 9
|
250
|
167
|
* If 125% does
not correspond to a standard ampere rating, the next higher standard rating
described in NEC Article 240-6 shall be permitted.
|
Primary Fuse Selection
Primary fuse selection is made according to rated primary current
(Ipri). To determine Ipri, the transformer rating (VA or KVA) and primary
voltage (Vpri) must be known as well as whether the transformer is single- or
three-phase. With this information, use the appropriate formula to determine
Ipri.
Once Ipri is known, select fuses according to Table 1 or 2 above.
Secondary Fuse Selection
Secondary fuse selection is made according to rated secondary
current (Isec). To determine Isec, the transformer rating (VA or KVA) and
secondary voltage (Vsec) must be known as well as whether the transformer is
single- or three-phase. With this information, use the appropriate formula to
determine Isec.
Once Isec is known, select fuses according to Table 2 above.
Insulation & Temperature
All Jefferson Electric transformers are designed and manufactured
with the best quality insulation available. There are classes of insulation
systems for different temperatures as defined by NEMA and ANSI.
Insulation classes are rated in °C rise above a specific ambient of 40°C
maximum. A transformer having a specific class of insulation, for example Class
220, can have an average winding temperature rise of 150°C with a maximum hot
spot temperature rise of 180°C. If the room ambient temperature is 40°C, then
the total temperature of the hottest spot would be 220°C. Jefferson Electric
transformers are designed to operate at rated load and voltage in maximum room
ambient temperatures of 40°C, average room ambient temperature not to exceed
30°C, and at altitudes not to exceed 3300 feet in accordance with NEMA
standards.
Insulating Classifications
The designations for insulation systems are numerical
classifications based on temperature ratings. Transformer ratings are based on
temperature rise. The accompanying table shows the designations.
Transformer and Insulation Systems Ratings
|
|||
Insulation Rating
|
Transformer Rating
|
Max. Ambient Temperature
|
Hot Spot Allowance
|
Class 105
|
55°C Rise
|
40°C
|
10°C
|
Class 150
|
80°C Rise
|
40°C
|
30°C
|
Class 180
|
115°C Rise
|
40°C
|
30°C
|
Class 220
|
150°C Rise
|
40°C
|
30°C
|
Overloads
Overloads exceeding the maximum allowable insulation temperature
can be tolerated, provided the overload is of short duration and is preceded
and followed by a period of operation at less than rated KVA (refer to ANSI
C57.96-1989, Tables 5,6,7). Overloading should be avoided unless approval is
obtained from the Jefferson Electric engineering department.
High Ambient Temperatures
Ambient temperatures above 30°C average over a 24-hour period and
40°C maximum require either a larger KVA rating or a special low temperature
rise transformer. A 150°C rise air cooled transformer can also be derated using
the formula of .4% KVA reduction for each degree centigrade above 30°C ambient
temperature.
Altitude Correction
For transformers above 3300 feet, reduce the KVA rating .3% for
each 330 feet above 3300 feet.
Transformer Sound
Transformers, like other electromagnetic devices, produce a
"hum" caused by the alternating flux in the transformer core. This
"hum", known as magnetostriction, is primarily produced at a fundamental
frequency of twice the applied frequency. The relative loudness depends on the
construction of the transformer, the manner of installation and the ambient
sound level at the site. The sound produced by a transformer has a fundamental
frequency of 120 Hz, accompanied by harmonics of 240, 360, 480, 600, etc.
Controlling Transformer Sound
Sound control becomes more important as power demands increase and
transformers are placed closer to their loads. Planning of transformer
placement and specification is especially important in designing high rise
apartments, hospitals and office buildings.
Proper installation can significantly reduce transformer noise.
For a quiet installation:
·
Consult your architect
about the location of the transformer while the building is being designed.
·
Install the transformer as
far as possible from areas where the sound could be objectionable.
·
Avoid placing near
multiple reflective surfaces such as in a corner, near a ceiling or floor, or
in a hallway.
·
Place sound-dampening pads
between the transformer and the mounting surface. (Pads may be neoprene with
sandwiched cork material or spring loaded with a rubber base.)
·
Use flexible conduit
couplings between the transformer and the wiring system. Mount the transformer
on walls or structural members sufficient to support its weight.
·
To avoid amplifying the
sound, mount the transformer on a surface with as large a mass as possible.
·
Judge transformer sound
only when the building is finished, occupied and functioning.
Sound Testing Standards
NEMA ST 1-4 (ANSI-C89.1) section 2.7 covers "Audible Sound
Level Test." For a thorough understanding of these tests it should be read
in its entirety.
Briefly, the transformer is tested at its rated frequency and
voltage under no-load conditions in a room which is 10 feet larger on all sides
than the transformer. The ambient sound level of the room must be at least 5
db, and preferably 10 db, below the ambient level plus the transformer level.
Five sound readings are taken with an approved sound meter one foot from each
side of the transformer enclosure and one foot above the enclosure. The sound
rating is the average of these five readings.
For three-phase transformers, the NEMA maximum allowable averages
of the readings in decibels are shown in the chart below.
Transformer NEMA Maximum Three-Phase db Ratings
|
||
KVA Rating
|
600V Class
|
5KV Class
|
0 - 9
|
40
|
45
|
10 - 50
|
45
|
50
|
51 - 150
|
50
|
55
|
151 - 300
|
55
|
58
|
301 - 500
|
60
|
60
|
501 - 700
|
62
|
-
|
701 - 1000
|
64
|
-
|
Troubleshooting
Guide
Hot transformer
|
|
Possible Cause
|
Suggested Remedy
|
High ambient temperature
|
Improve ventilation or relocate unit to
cooler location.
|
Overload
|
Reduce load; reduce amperes by improving
power factor with capacitors; check for circulating currents for paralleled
transformers - different ratios or impedances; check for open phase in delta
bank.
|
High voltage
|
Change circuit voltage, taps.
|
Insufficient cooling
|
If other than naturally cooled, check fans,
pumps, valves and other units in cooling systems.
|
Winding failure - incipient fault
|
See "No voltage - unsteady
voltage" below.
|
Short-circuited core
|
Test for exciting current and no-load loss;
if high, inspect core, remove and repair; check core bolt, clamps and
tighten; check insulation between laminations; if welded together, return to
factory for repair or replacement.
|
High harmonic loads
|
Measure neutral current - replace with
K-rated transformer
|
Noisy transformer
|
|
Possible Cause
|
Suggested Remedy
|
Overload
|
See "Hot transformer" above.
|
Metal part ungrounded, loose connection
|
Determine part and reason; check clamps,
cores and parts normally grounded for loose or broken connections, missing
bolts or nuts, etc.; tighten loose clamps, bolts, nuts; replace missing ones.
|
External parts and accessories in resonant vibration
|
Tighten items as above; in some cases,
loosen to relieve pressure causing resonance and install shims.
|
Incipient fault - core or winding
|
See above under "Hot transformer."
|
No voltage - unsteady voltage
|
|
Possible Cause
|
Suggested Remedy
|
Winding failure - lightning; overload;
short-circuit from foreign object or low strength dielectric
|
Check winding; remove foreign object or
damaged material; repair or replace parts of insulation materials.
|
Rust and paint deterioration
|
|
Possible Cause
|
Suggested Remedy
|
Weather, pollution, corrosive or salt
atmosphere; overloads
|
Remove rust and deteriorated paint; clean
surfaces; repaint with proper paints and sufficient coatings.
|
Excessive heating discoloration
|
If excessive heating discoloration occurs,
check sizing, input voltage, or loading amps.
|
Hot neutral line
|
|
Possible Cause
|
Suggested Remedy
|
Overload
|
Too small neutral conductor: replace. Severe
unbalance between phase: rebalance and equalize loads.
|
One leg of wye bank open
|
Check associated fuse. If blown, remove
cause and replace. Check for open circuit in winding of transformer in bank.
Measure odd harmonic amps with RMS meter.
|
Voltage unbalanced
|
|
Possible Cause
|
Suggested Remedy
|
Open neutral unbalanced loads
|
Check neutral connections. See "Hot
neutral line" above.
|
Voltages high and unbalanced
|
|
Possible Cause
|
Suggested Remedy
|
Open neutral on wye bank ground in winding
of one transformer in wye
|
Check neutral connections and load balance.
Check values of voltages between phases and phase-to-ground voltages. Vector
should indicate source of trouble.
|
No voltage - one phase of delta
connected bank
|
|
Possible Cause
|
Suggested Remedy
|
Grounds on two legs of delta (delta collapse
- loads "single phasing")
|
Remove grounds from at least one leg of
delta source.
|
Overloads on two delta bank
|
|
Possible Cause
|
Suggested Remedy
|
Open in third transformer of bank; operating
in open delta
|
Check fuses on supply to their bank; check
winding of transformers in third transformer for continuity.
|
Low voltage on two phases of
delta
|
|
Possible Cause
|
Suggested Remedy
|
Open in one phase of delta supply; two
transformers now connected across one same phase
|
Check fuse on supply; check supply circuit
back to source for open circuit.
|
Frequently Asked Questions
Single and Three Phase Transformer Questions
Can I connect a single-phase transformer to a three-phase source?
Yes, and the transformer output will be single-phase.
Simply connect any two wires from a 3- or 4-wire source to the transformer's
two primary leads. Three single-phase transformers can be used for three-phase
applications. They can be used in delta-connected primary and wye or delta-connected
secondary. To avoid an unstable secondary voltage, NEVER connect wye primary to
delta secondary.
Can I use a transformer to change three-phase to single-phase?
It is not possible for a transformer to present a
balanced load to the supply and deliver a single-phase output. Changing
three-phase to two-phase, and vice-versa, can be done using special circuitry
with standard dual-wound transformers.
Temperature and Heat Related Transformer Questions
Can Transformers be used in parallel?
It is very common for transformers to be placed in
parallel service. To provide maximum efficiency and voltage, impedance values
must match closely for each transformer involved. A failure to match voltage
and impedances will cause unbalanced loading for the transformers and may lead
to "overheating" or premature failure.
What is meant by a transformer's temperature rise?
A transformer's rated tempature rise (degrees Celsius)
is the avarage temperature of the transformer's windings over an ambient
temperature of 40 °C.
Why is the transformer case hot?
Transformers are designed to operate at a specific
load. As transformers are overloaded, losses generated increases which reults
in a potential case for heating. If a transformer is properly sized for a
specific application, no excessive heating should be present.
How do I know when the temperature rise is too high?
Touch is a poor indicator of proper transformer
opertaing temperature. Properly designed transformers can reach 50 °C (112 °F)
above ambient temperature. In an ambient temperature of 20 °(60 °F) the total
temperature can reach 70 °C (190 °F), which is too hot to touch. Thermometers
are the best way to determine the temperature.
Do I need special transformers for high ambient temeratures?
If you have an immediate need that cannot wait for a
custom-built transformer, you can de-rate a standard transformer. For each 10
°C above 30°C, de-rate the maximum loading by 4% (30°C = 100% ; 40 °C = 96%; 50
°C = 92% ; 60 °C = 88% ).
Reverse Transformer Questions
What about transformers in reverse?
Transformers connected in reverse, to proper input
voltages, will provide correct nameplate voltage output, albeit reversed.
However, for transformers rated 2 KVA and below, the output voltage would be
less than the nameplate rating, since smaller KVA transformers have a greater
turns ratio compensation on their low voltage windings.
CAUTION: When reverse connecting a delta-wye
transformer, a wye primary will be created. Wye primaries may cause problems
and are not recommended. If a wye primary must be used, do not connect the
neutral.
Why do you not recommend reverse connecting a delta-wye
transformer?
You can reverse wire the delta-wye, the primary wye is
connected without using the neutral (X0) and it turns into a delta-delta.
What would happen if you connected the neutral on the wye
primaries if reverse connected? Would this short, overheat?
The problem is that you could get a fault current on
the neutral which may not trip the breaker in case of a problem.
Type of Transformers Questions
What is an isolating transformer?
An isolating transformer has the primary and secondary
windings connected magnetically, but not electrically. Also referred to as an
"insulating" transformer.
What is a non-linear (K-factor) transformer?
A transformer that is designed to handle the odd
harmonic current loads caused by much of today's modern office equipment. A
non-linear transformer has a K-factor rating that is an index of its ability to
supply harmonic content in its load current while remaining within its
operating temperature limit.
What is a drive isolation transformer?
A drive isolation transformer is designed for use with
motor drives. It must isolate the motor from the line and handle the
overcurrent mode during motor startup. It is important to heed the drive
manufacturer's recommendations for transformer KVA.
What is a buck boost transformer?
Buck-boost transformers are single-phase isolated
distribution transformers having four windings instead of two. They can be
connected as an autotransformer to buck (reduce) or boost (raise) the line
voltage from 5 - 20%. Typical reduced secondary voltages are 12, 16, 24, 32, or
48 volts. Commonly found raised secondary voltages are 208 to 230 or 240 volts.
Copper and Aluminum Transformer Questions
What are the differences between copper and aluminum windings?
We design our copper and aluminum units to meet the
same specifications. Aluminum coils need to use larger wires, but the user does
not see any difference. The copper coils are physically smaller, but we put
them in the same enclosure as the Aluminum, so the user will not see any
difference. The terminals are the same, so the user will not see any
difference. Most wiring lugs are tin-plated so there is no problem connecting
the transformer to aluminum or copper wires.
Copper has better conductivity but less life expectancy, correct?
Conductivity is addressed in the design by using
larger wire in aluminum units. There is no difference in life expectancy for
copper.
Anything else?
The only real difference is that Copper costs more.
Voltage and Electrical Load Transformer Questions
How do I determine the electrical load?
Obtain the following standard nameplate or instruction
manual data for the equipment (the load) to be powered: :
·
Voltage required by the
equipment
·
Amperes or KVA capacity
required by the equipment
·
Required frequency of
source voltage in Hz (cycles per second)
·
Determine whether the load
is designed to operate on a single- or three-phase supply (see Page 4 for
additional information)
·
Others to order
What is the supply voltage?
The supply voltage may be higher or lower than the
voltage required by the load. However, the frequency of the two may not differ.
If your load ratings are not expressed in KVA, use the
load voltage and amperage to determine the KVA.
For single-phase: VA = volts x amperes KVA = VA/1000
For three-phase: VA = volts x amperes x 1.73 KVA = VA/1000
Once you have a KVA rating, then select a transformer
from the charts in the appropriate section of this catalog by matching the
primary and secondary voltages determined above.
What is voltage regulation in a transformer?
The voltage difference between loaded and unloaded output.
To provide the proper secondary load voltage, extra primary windings cause the
no-load secondary voltage to be 3-5% higher than the load voltage. Also known
as "compensated windings."
What will happen if transformers are operated at non-nameplate voltages?
A transformer is designed using specific ratios that
relate to the rated KVA, primary voltage and secondary voltage proportionally.
Operating a transformer above or below the nominally designed primary voltage
will reflect a proportional increase or decrease in secondary output levels.
Extreme caution must be observed when overvoltage levels exist. Excessive input
voltage will cause higher core losses, increased noise and elevated
temperatures. Overvoltages for any extended period of time have a significant
effect on insulation breakdown and transformer failures. Transformers can be
specifically designed for extreme voltage conditions if initial specifications
state those requirements.
Miscellaneous Transformer Questions
Are your transformers used in residential applications?
Yes
Are there additional standards required for residential
applications (building codes, etc.)?
We meet the general NEC requirements as far as
residential applications, but there could be specific local code requirements.
What is the general life expectancy of your transformers under
normal use?
20-40 years for typical use.
What type of terminations are provided on Jefferson Electric
transformers?
Jefferson Electric dry type transformers are provided
with the following primary and secondary terminations:
·
Encapsulated wire leads
·
Ventilated terminals
·
Machine Tool Terminals
·
Control leads
·
Others to order
Can transformers be operated at different frequencies?
A 60 Hz design is physically smaller than a 50 Hz
design. DO NOT use 60 Hz rated transformers on 50 Hz service. Without special
designs, higher losses and greater heat rise will result. Operating 60 Hz
transformers at higher frequencies may simply provide less voltage regulation.
What would be the result of overloading dry type transformers?
All Jefferson Electric transformers are designed to
accommodate short periods of overloading. As the overload becomes excessive and
the duration increases, the transformer will experience a percent loss of life.
Prolonged overloading generates excessive heating which results in insulation
deterioration and ultimately transformer failure. Contact your Jefferson
Electric application engineer to determine loading for your unique application.
Can I achieve specific sound levels in a transformer?
Whenever noise is a concern, but before selecting a
transformer, assure yourself that the sound levels represented have been
measured in accordance with the NEMA standards. If your requirement is lower
than that available from the manufacturer’s standard product, request a
specific sound level on your RFQ or bid. (See Transformer Sound Page 99.)
Energy Efficiency Transformer Questions
Why do the energy efficiency ratings only apply to ventilated
transformers?
This is what the government says. The law targets the
"Distribution" transformers which are the most common and are
typically oversized which results in the "wasted" electricity of
powering a large unit 24/7.
Are the TP-1 Energy Efficiency ratings exceeded?
We need to meet the ratings, so some may be exceeded
slightly. We see no reason to provide a higher level of efficiency since this
adds to the cost of the units. It is very expensive to get the next 1% of
efficiency and we are already over 97 to 98% depending on the size of the unit.
Are these transformers more efficient than any of our competitors?
Everyone needs to meet the same requirements.
Can you provide any efficiency information, now that you have
obtained the Canadian High Efficiency Approval? For example, different loading
conditions besides 35% load.
35% was chosen as the test requirements for the new
law. There are calculators on the web to check the energy usage and cost
savings for switching to a TP-1 transformer, but no one really cares anymore
since you must choose the TP-1 units today. Also, to use the calculators, you
need to know the specific core loss and coil loss for each model of transformer
and this is not typically available.
Do you have any examples that may show cost savings of this
transformer?
Our TP-1
whitepaper shows
a typical ROI of 5 years to recover the cost on installing a new TP-1
transformer, but most users will not change a transformer.
Reducing Distribution
Losses Without Breaking the Bank
By Steve Eckles, El Paso Electric Co.
With
increasing concerns about energy efficiency, distribution loss reduction is
again assuming a role of prominence in the utility industry. For most North
American utilities, the 1 percent or 2 percent of additional peak capacity that
could be derived through loss reduction would provide significant savings.
Besides
the financial implications, low-loss design also improves reliability, lessens
power quality concerns, and better accommodates customer load growth. And,
there’s an environmental twist to lowering distribution losses: Lowering
distribution losses reduces the amount of pollutants and greenhouse gasses from
hydro-carbon based power plants.
Utilities
can reduce distribution losses by concentrating on the design and operation of
the distribution system. However, some of these loss-reduction measures require
financial commitment, forcing energy-conscious utilities to balance loss
savings with capital investment.
Distribution Loss Modeling and Reduction Strategies
Distribution
technical losses, i.e. losses resulting from operational inefficiencies, are
generally divided into two types: load and no-load. For simplicity of modeling,
both load and no-load real power losses in a distribution system can be modeled
as resistors RL and RNL in a shunt circuit as shown in Figure
1.
Load
losses represented by RL vary
quadratically with system load. They are also referred to as resistive,
conductor, copper, or I2R losses. Constant no-load losses,
represented by RNL, are driven by the presence or application of AC
voltage. The amount of load has no appreciable effect on no-load losses. The
vast majority of these losses are from distribution transformer excitation.
Underground cable dielectric losses are also a small component of no-load
losses.
In
a well-run, highly capitalized distribution system, losses are approximately 3
percent to 5 percent. In neglected systems with poor planning criteria and
design standards, losses may increase to 5 percent to 7 percent or higher. Peak
losses occur during peak load when generation pricing is at its highest and
distribution equipment thermal capacity is often stressed.
Main Causes of Distribution Losses
Physicists
may study phenomena such as dielectric and induction losses, but the most
consequential distribution losses are due to resistive copper losses and
transformer excitation.
Conductor
power losses result from electron flow (current) through resistance in primary,
secondary, and transformer conductors regardless of conductor material (e.g.
copper, aluminum, aluminum-alloy, etc.). Feeder voltage, conductor length and
size, power factor, load factor, loading, and phase current balance all
determine copper losses.
The
conductor current contribution to technical power losses is higher than that
for conductor resistance as shown in the resistive power loss equation Ploss = I2 x R, where: Ploss is power loss in watts; I is current
measured in amperes, and R is resistance measured in ohms.
Conductor
heating is proportional to the square of the current; therefore, conductor
power losses will double if the current increases by only 41 percent as
represented in Figure 2, next page.
Benefits of Higher Primary Operating Voltage
To
minimize copper power loss is to minimize circuit resistance and current. As is
evident by the current squared term in the resistive power loss equation (Ploss = I2R), reducing conductor
current results in dramatic savings. This equation reveals that two half-loaded
feeders each have one-fourth the copper losses of one fully loaded feeder,
given all the feeders are the same length and use the same conductor size. This
suggests that copper losses could be halved by building double-circuit
distribution primary; however, capital costs would drastically increase.
Therefore,
the recommended design practice to economically decrease conductor losses through current
reduction is toincrease primary
voltage. Apparent power (kVA) in a conductor is proportional to voltage and
current (kVA = kV x I); doubling primary operating voltage will cut the
conductor current in half for the same feeder power flow. Hence, by the
resistive power loss equation, the resulting copper loss is 25 percent that of
the original voltage using the same feeder conductor and length (see Figure 3).
Increased costs for higher voltage class insulation are relatively small
compared to total feeder costs. Additionally, the rated feeder power capacity
also doubles when doubling the voltage. It is beyond the scope of this article
to delve into voltage drop and power flow equations and calculations; however,
simple power flow programs show that doubling operating voltage will not only
reduce power loss but will also enable more customers to be served on longer
feeders with less power loss and less percentage voltage drop. This results in
lower overall capital and operating costs.
The
second variable in the resistive power equation, conductor resistance, is
inversely proportional to its cross-sectional area. Hence, larger diameter
conductors produce less loss than smaller conductors of the same material for
the same current. Voltage drop will also be less with larger diameter
conductors; however, construction costs are higher. Larger overhead conductor
often brings with it the added expense of stronger poles, cross-arms, or
shorter span lengths (more poles per mile). The additional cost makes it hard
to justify larger distribution conductor on the basis of lowering power losses.
More capacity and less voltage drop are better drivers for larger conductor.
Legacy 4160-Volt Systems
Many
utilities have pockets of 4160 voltage systems in older parts of town
surrounded by higher voltage feeders. At this lower voltage, more conductor
current flows for the same power delivered, resulting in higher I2R
losses. Conversely, converting old 4160-volt feeders to higher voltage is
capital-intensive and often not economically justifiable unless the line is
already in poor condition and needs major improvements. If parts of the
4160-volt primary are in relatively good condition, installing multiple
step-down power transformers at the periphery of the 4160-volt area will reduce
copper losses by injecting load current at more points (i.e., reducing overall
conductor current and the distance traveled by the current to serve the load).
Reactive Power Compensation
Both
customer inductive loads and current through inductive utility conductors
require that reactive power be supplied to the distribution system. This
reactive power current lags the real power current by 90 degrees (4.2 ms in 60
Hz systems, 5 ms in 50 Hz systems). A feeder with 113 amps of current at a
lagging power factor of 85 percent has 53 amps of inductive current added
vectorally at 90 degrees to 100 amps of real power current. Both real power and
inductive current are supplied from utility generation through transmission
lines, substation transformers, and finally distribution feeders unless other
sources of reactive power are added. Fortunately, shunt (phase-to-ground)
distribution capacitors economically supply inductive current. Adding feeder
capacitors to supply the 53 amps of inductive current reduces total feeder
current to its real power component of 100 amps. The 13 percent feeder current
reduction translates into approximately 28 percent lower I2R losses.
Additionally, reducing total current frees up system capacity and reduces
feeder voltage drop resulting in a “flatter” feeder voltage profile.
Installing multiple step-down power transformers at the periphery of the 4160-volt area will reduce copper losses by injecting load current at more points. |
A
number of utilities have adopted the “two-thirds rule,” or some variant, for
distribution capacitor placement. It calls for installing a quantity of
capacitive volt-amperes reactive (VARs) equal to two-thirds of the total feeder
peak inductive VARs at a distance of two-thirds of the overall feeder length
from the substation. The rule works best for a feeder of constant load that is
uniformly distributed along the feeder’s length. These two conditions are more
theoretical than realistic and are mostly found in textbooks and technical
papers.
Feeder
reactive power varies with load throughout the day and throughout the year. If
reactive power compensation were only supplied with fixed capacitor banks, it
would likely result in over-compensation (too much capacitive current) during
light feeder loading and under-compensation (not enough capacitive current)
during peak load. This increases total current-leading to increased I2R
loss-and possible over-voltage (steady-state capacitive current raises voltage
over conductor inductance) during light feeder loading.
By using a combination of fixed (left) and switched (right) capacitor banks, reactive power compensation will better track load and minimize losses. |
Placing
fixed capacitors according to the two-thirds rule (or a similar variation) can
be performed relatively quickly with minimal engineering time and will likely
produce immediate power and energy savings. However, it does not meet full
reactive power compensation (i.e. unity power factor where real power current
equals total current) to produce the least feeder I2R losses at
peak. By using a combination of fixed and switched capacitor banks, reactive
power compensation will better track the load and minimize losses. This has
proven to be economical and well worth the extra effort.
To
save the most energy annually through capacitive reactive power compensation,
the amount of fixed capacitance (VARs) should approximately equal the feeder’s
reactive power requirements at minimum annual load. Switched capacitor banks
should then be added to the fixed capacitor banks on the feeder until the total
peak feeder reactive power requirements are met. Modeling distribution feeders
in a power flow computer program will yield the most economical fixed and
switched capacitor placement. Without the luxury of power flow modeling,
capacitor bank placement can be determined by placing capacitors near
concentrated or lumped feeder loads using an 85 percent load power factor approximation.
It is worth noting that capacitor bank current can flow both downstream and
upstream of the bank itself-ideally half going each way. Hence, capacitors
should rarely be placed close to the feeder breaker unless a fair amount of
load is concentrated there. Likewise, it is best not to place capacitors at the
end of distribution feeders unless load or voltage needs dictate it.
Low-voltage concerns during contingency backfeeding may also call for
capacitors near the feeder breaker.
Capacitors
may be switched according to a variety of factors, so selecting a capacitor
switching method warrants a more detailed discussion. Switching determination
methods (i.e. trip or close decisions) include: VAR requirements, voltage,
ambient temperature and time-of-day. Switching on reactive power requirements
with voltage override is best for reducing power losses while maintaining
proper operating voltage. The simplest way to switch by VAR requirements is
installing a local switch controller that uses a single-phase voltage
transformer and a single-phase current transformer (CT) to determine the power
factor and current magnitude immediately downstream of the capacitor bank and
closes it on adjustable settings. The same local capacitor controller can house
voltage override controls to close the capacitor bank for low voltage and trip
it for high voltage.
Unfortunately,
it can be difficult and time-consuming to evaluate whether local capacitor bank
switch controllers are working properly after several years of service.
Receiving a graph of a feeder’s VARs (reactive power) over time should show
capacitors switching on and off as needed. If VAR information is available from
SCADA to a local control center, it may prove more economical to employ a more
widespread approach of switching feeder capacitors remotely based on feeder VAR
data. A limited number of software and hardware companies (such as Cannon
Technologies and RCCS) offer systems that initiate capacitor switching commands
based on feeder SCADA.
For
simplicity, signals can be sent one-way via utility radio, local paging, and
cellular control channel (such as Telemetric). Software monitors feeder VAR
response after a switching command is sent to confirm capacitor operation and
logs suspected switching failures. Capacitor control receivers may be equipped
with voltage override. Software allows adjustments in feeder VAR requirements
and also permits capacitor banks to be manually switched to respond to abnormal
feeder voltage or transmission system needs. Operating one distribution
capacitor may be imperceptible on the transmission system, but a global command
to switch all distribution capacitors on or off should be evident. For
wide-scale implementation, SCADA VAR control capacitor switching is recommended
due to its response to reactive power compensation needs with the flexibility
of global or individual capacitor manual override. Using such a system, one
utility reports replacing all fixed capacitors with switched ones to
automatically flag cases of blown fuses as the software systematically cycles
capacitors during early morning hours to test them.
Transformer Sizing and Selection
Typically,
distribution transformers use copper conductor windings to induce a magnetic
field into a grain-oriented silicon steel core to step feeder voltage down for
customer use. Therefore, transformers have both load loss and no-load core
loss. As in other conductors, transformer copper losses vary with load based on
the resistive power loss equation (Ploss= I2R). For some
utilities, economic transformer loading means loading distribution transformers
to capacity-or slightly above capacity for a short time-in an effort to
minimize capital costs and still maintain long transformer life. However, since
peak generation is usually the most expensive, total cost of ownership (TCO)
studies should take into account the cost of peak transformer losses.
Increasing distribution transformer capacity during peak by one size will often
result in lower total peak power dissipation-more so if it is over-loaded.
Transformer
no-load excitation loss, also known as core or iron loss, occurs from a
changing magnetic field in the transformer core whenever it is energized. Core
loss varies slightly with voltage but is essentially considered constant. Fixed
iron loss depends on transformer core design and steel lamination molecular
structure. Improved manufacturing of steel cores and introducing amorphous
metals (such as metallic glass) have reduced core losses. Through faster
material cooling, mass-produced metallic glass (or MetGlass ) ribbons were
developed by Allied Signal (now Honeywell) in the 1990s that reduced core loss
by 60 percent compared to conventional grain-oriented silicon steel cores.
Copper losses can be slightly higher in metallic glass core transformers but
overall loss at rated capacity is less.
Utilities
must determine if reduced energy losses more than offset the price premium for
more efficient transformers. In general, early transformer replacement programs
are not economically warranted.
Feeder Phase Current and Load Balancing
Once
a distribution system has been built, some of the easiest loss savings comes
from balancing current along three-phase circuits. Feeder phase balancing also
tends to balance voltage drop among phases giving three-phase customers less
voltage unbalance. Amperage magnitude at the substation doesn’t guarantee load
is balanced throughout the feeder length. Feeder phase unbalance may vary
during the day and with different seasons. Feeders are usually considered
“balanced” when phase current magnitudes are within 10 percent (based on the
average current among phases). That is: [(highest phase current - lowest phase
current)/average phase current]< 0.1.
Similarly,
balancing load among distribution feeders will also lower losses assuming
similar conductor resistance. This may require installing additional switches
between feeders to allow for appropriate load transfer.
Load Factor Effect on Losses
Typical
customer power consumption varies throughout the day and over seasons. Residential
customers generally draw their highest power demand in the evening hours when
they arrive home from work and school and activate the heating or cooling
system, turn on lights, and prepare dinner. Conversely, commercial customer
load profiles generally peak in the early afternoon. Because current level
(hence, load) is the primary driver in distribution power losses, keeping power
consumption more level throughout the day will lower peak power loss and
overall energy losses. Ideally, peaks should be “shaved” to fill in troughs. A
common measurement of load variation is “load factor.” It ranges between zero
and one and is defined as the ratio of average load in a specified time period
to peak load during that time period. For example, over a 30-day month (720
hours) peak feeder power supplied is 10 MW. If the feeder supplied a total
energy of 5,000 MWh, the load factor for that month is 0.69 (5,000 MWh/(10MW x
720 hours).
Lower
power and energy losses are achieved by raising the load factor, which, evens
out feeder demand variation throughout the feeder. Increasing the load factor
has been met with limited success by offering customers “time-of-use” rates.
That is, companies use pricing power to influence consumers to shift
electric-intensive activities (such as, electric water and space heating, air
conditioning, irrigating, and pool filter pumping) to off-peak times. With
financial incentives, some electric customers are also allowing utilities to
interrupt large electric loads remotely through radio frequency or powerline
carrier during periods of peak use.
Utilities
can try to design in higher load factors by running the same feeders through
residential and commercial areas.
Conclusion
With
increased concern for generation and transmission efficiencies, utilities will
find an increasingly compelling business case to adopt distribution loss
reduction strategies. The core of these strategies involve reduction in both
circuit current and resistance. Distribution feeder design philosophy may be
adapted to reduce feeder current by using higher operating voltage and a higher
quantity of feeders that are shorter in length. In addition, modifying
standards to specify larger conductor sizes will reduce resistance. Current may
also be reduced in existing feeders by adding fixed and switched shunt
capacitor banks.
Increasing
new transformer sizes may reduce peak power loss but may result in higher
annual energy loss due to increases in no-load losses. Some utilities may
benefit by paying more up front for higher-efficiency transformers and
recapture those costs through loss savings over the next 20-plus years.
Balancing current on existing feeder phases and redistributing load among
feeders will also improve economic operation of existing systems.
Distribution
loss reduction takes some engineering analysis, but it will pay off for years
to come.
Steve Eckles has
been a distribution engineer for 14 years at El Paso Electric Company and is a
licensed PE in New Mexico and Texas.
0 Response to "Sizing and Selecting a Transformer"
Post a Comment