Welcome to [Dunia Electrical] >>Download Software ETAP disini >>Daftar Training ETAP disini

How to setting Relay Coordination

1. Standard and Code
  • NEC Article 430-32 (Continuos - Duty Motors)
  • NEC Article 430-126 (Rating of Motor Control Apparatus)
  • IEEE Std 141-1976, IEEE Recommended Practice for Electrical Power Distribution for Industrial Plants
  • IEEE Std 242-1986, IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power System
  • IEEE C37.101-1993, IEEE Guide for AC Generator Ground Protection
  • IEEE C37.102-1987, IEEE Guide for AC Generator Protection

2. Principles of Protective Relay Application

Fault protection relaying can be classified into two groups, primary relaying which should function first in removing faulted equipment from the system, and backup relaying which functions only when primary relaying fails. For complete explanation, see IEEE Std 141-1976 (IEEE Recommended Practice for Electric Power Distribution for Industrial Plants).

3. Methodology / Calculation Criteria

The study is based on the data and parameter as defined below:
  • The study is performed by Power Plot version 2.5. The Power Plot v.2.5 has provided some fixtures which used as parameter in this project as follow:
  • Transformer thermal damage and inrush currentcurve
  • Cable thermal damage curve
  • Motor Starting Curve
  • MCP & MCCB curve
  • User curve
  • Available 3 phase short circuit current at all relevant buses

3.1 Generator Protection

3.1.1 Generator Data


Gas Turbine Generator
”A/B”
Diesel Engine Generator

Engine Manufacturer


Generator manufacturer


kW rating
1100
650
kV rating
0.4
0.4
PF rating
0.8
0.8
Frequency Rating
50
50
FLA Rating (A)
1985
1173
Reactance (unsat)


Synchronous, Xd (%)
103.6
303.42
Transient, X’d (%)
13.8
22.1
Subtransient, X”d (%)
11
15.51
Motoring Power (kW)
120

Unbalanced Capability
see attachment #2
see attachment #2

3.1.2 Generator Protection



Generator protection is using GE - Multilin SR 489. The 489 Generator Management Relay is a microprocessor-based relay designed for the protection and management of synchronous and induction generator.
Refer to below paragraph for the SR489 relay setting.







3.1.3 Setpoint / System Setup

Current Sensing

Gas Turbine Generator
”A/B”
Diesel Engine Generator

Phase Current


Primary CT
2500 Amps
1200 Amps
Ground Current


Ground CT Type
5 A Secondary
5 A Secondary
Ground CT Ratio
50/5
50/5
Voltage Sensing

Gas Turbine Generator
”A/B”
Diesel Engine Generator

Voltage Transformer


VT Connection Type
Open Delta
Open Delta
Transformer Ratio
33.3
33.3
Generator Parameters

Gas Turbine Generator
”A/B”
Diesel Engine Generator

Generator Rated MVA
1.375 MVA
0.812 MVA
Generator Rated Power Factor
0.8
0.8
Generator Voltage Phase-Phase
400 V
400 V
Generator Nominal Frequency
50 Hz
50 Hz
Generator Phase Sequence
ABC
ABC
Serial Start/Stop Initiation
None


3.1.4 Setpoint / Digital Input

Breaker Status

Gas Turbine Generator
”A/B”
Diesel Engine Generator

Breaker Status
Breaker Auxiliary A
Breaker Auxiliary A
General Purpose
None
Predefined
None
Generator Switch Status
None

3.1.5 Setpoint / Output Relay


Gas Turbine Generator
”A/B”
Diesel Engine Generator

Relay Reset Mode


R1 Trip
All Resets
All Resets
R2 Auxiliary
All Resets
All Resets
R3 Auxiliary
All Resets
All Resets
R4 Auxiliary
All Resets
All Resets
R5 Alarm
All Resets
All Resets
R6 Service
All Resets
All Resets



3.1.6 Setpoint / Protection

3.1.6.1 Current Element

Overcurrent Alarm
·       Consideration/formula
This feature is intended to give the time for operator to analyze and asses the situation when overload  of generator occurred.
·       Setting

GPR for GTG
”A/B”
GPR for DEG

Overcurent Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
Overcurent Alarm Level
1.01 x FLA
1.1 x FLA
Overcurent Alarm Delay
3 s
3 s
Overcurent Alarm Event
On
On
Offline O/C
·       Consideration/formula
This feature is active only when generator is OFFLINE and uses the neutral measurements end CT. It is set more sensitive than differential relay to detect high impedance phase faults.
Since the breaker auxiliary contacts wired to the 489 Breaker Status Input may not operate at exactly the same time as the main breaker contact, the time delay should be coordinate with the difference of the operation times.
·       Setting

GPR for GTG
”A/B”
GPR for DEG

Offline Overcurrent Trip
Unlatched
Unlatched
Assign Trip Relay (1-4)
1, 3
1, 3
Offline Overcurrent Pickup
0.05 x CT
0.8 x CT
Offline Overcurrent Delay
10 Cycles
10 Cycles



Inadvertent Energize
·       Consideration/formula
This relay is intended to protect a poor synchronizing by “U/V or Offline”.
·       Setting

GPR for GTG
”A/B”
GPR for DEG

Inadvertent Energize Trip
Unlatched
Unlatched
Assign Trip Relay (1-4)
1, 3
1, 3
Arming Signal
UV and Offline
UV and Offline
Inadvertent Energize  O/C Pickup
0.15 x CT
0.15 x CT
Inadvertent Energize Pickup
0.95 x  Rated Volt
0.95 x  Rated Volt
Phase Overcurrent
·       Consideration/formula
This relay is as backup protection and shall be coordinated with downstream “relay” to avoid overlapping protection. (see relay coordination case #5 & #6 on the paragraph 4.7 & 4.8 )
·       Setting

GPR for GTG
”A/B”
GPR for DEG

Phase Overcurrent Trip
Latched
Latched
Assign Trip Relay (1-4)
1, 3
1, 3
Enable Voltage Restraint
No
No
Phase Overcurrent Pickup
2 x CT
1.4 x CT
Curve Shape
Definite Time
Definite Time
Overcurrent Curve Multiplier
2
2
Overcurrent Curve Reset
Instantaneous
Instantaneous
Negative Sequence
·       Consideration/formula
The relay should be set to lower than I22t limit of the generator being protected. The actual generator unbalance current capability shall be plotted in the common scale (Log-Log) and then the relay (constant K) can be adjusted to get optimum setting of this relay
·       Setting

GPR for GTG
”A/B”
GPR for DEG

Negative Sequence Alarm
Latched
Latched
Assign Alarm Relay (2-5)
5
5
Neg. Sequence Alarm Pick-up
5% FLA
5% FLA
Negative Sequence Alarm Delay
5 s
5 s
Negative Sequence Alarm Event
On
On
Negative Sequence O/C Trip
Latched
Latched
Assign Trip Relay (1-4)
1, 3
1, 3
Neg. Sequence Trip Pick-up
20% FLA
20% FLA
Neg. Sequence O/C Constant K
5
5
Neg. Sequence O/C Max. Time
125 s
125 s
Neg. Sequence O/C Reset Rate
150 s
150 s
Ground O/C
The ground O/C protection is not used since generator is grounded through a ground fault neutralizer (HRG device) to operate alarm and to give the time for operator to analyze and asses the situation and tripping will be delayed as long as an hour or two to permit fault insulation.
Phase Differential
·       Consideration/formula

·       Setting

GPR for GTG
”A/B”
GPR for DEG

Phase Differential Trip
Unlatched
Unlatched
Assign Trip (1-4)
1, 2, 3
1, 2, 3
Differential Trip Min Pick-up
0.1 x CT
0.1 x CT
Differential Trip Slope 1
10%
10%
Differential Trip Slope 2
20%
20%
Differential Trip Delay
10 cycles
10 cycles
Ground Directional
Not applicable since the 59N is not used in this project.



High-set Phase O/C
·       Consideration/formula
This element can be used as back-up feature to overcurrent. It is set above the maximum current contribution from generator when parallel operation.
The maximum current contribution from GTG and DEG to the fault are 18.7kA & 10.8kA. 
·       Setting

GPR for GTG
”A/B”
GPR for DEG

High-Set Phase O/C Trip
Unlatched
Unlatched
Assign Trip (1-4)
1, 3
1, 3
High-Set Phase O/C Pickup
2.2 x CT
1.6 x CT
High-Set Phase O/C Delay
0.6s
0.6s


3.1.6.2 Voltage Element

Undervoltage
·       Consideration/formula
Refer to General Electrical Design Specification PS-1100-ELE-001 voltage drop on the bus max. drop 6% at steady state condition and 15% at transient condition.
·       Setting

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Undervoltage Alarm
Unlatched
Unlatched
Assign Alarm Relays (2-5)
5
5
Undervoltage Alarm Pickup
0.87 x Rated
0.87 x Rated
Undervoltage Alarm Delay
2.3 s
2.3 s
Undervoltage Trip
Latched
Latched
Assign Trip Relays (1-4)
1,3
1,3
Undervoltage Trip Pickup
0.85 x Rated
0.85 x Rated
Undervoltage Trip Delay
2 s
2 s
Undervoltage Curve Reset Rate
3 s
3 s
Undervoltage Curve Element
Curve
Curve
Overvoltage
·       Consideration/formula
Generator overvoltage may occur without necessarily exceeding the volts/Hz limits of the machine. In general, this not problem with steam and gas turbine generators because of the rapid response of the speed-control system and voltage regulator.
The instantaneous unit is generally set to pickup at about 130% - 150% of nominal voltage (see IEE C17.102-1987).
·       Setting

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Overvoltage Alarm
Unlatched
Unlatched
Assign Alarm Relays (2-5)
5
5
Overvoltage Alarm Pickup
1.05 x rated
1.05 x rated
Overvoltage Alarm Delay
2 s
2 s
Overvoltage Trip
Latched
Latched
Assign Trip Relays (1-4)
1,3
1,3
Overvoltage Trip Pickup
1.1 x rated
1.1 x rated
Overvoltage Trip Delay
1 s
1 s
Overvoltage Curve Reset Rate
3 s
3 s
Overvoltage Curve Element
Curve
Curve
Volt / Hertz
Not applicable since it is used for protection integral generator and transformer


Phase Reversal
·       Consideration/formula
This feature is intended to protect phase rotation.
·       Setting

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Phase Reversal Trip
Latched
Latched
Assign Trip Relays (1-4)
1, 3
1, 3
Underfrequency
Not applicable since using individual Relay 81 for underfrequency  detection
Overfrequency
None
Neutral O/V (Fund.)
Not applicable since no detection device
Neutral U/V (3rd)
Not applicable since no detection device
Loss of Excitation
·       Consideration/formula



A. Loss of excitation setting for Gas Turbine Generator (GTG)
                                        = 16.02 W
                          X’d (sec) = Zbase x X’dpu
                                        = 16.02 x 0.138 = 2.21 secondary ohms
                          Xd (sec)  = Zbase x Xdpu
                                        = 16.02 x 1.036 = 16.59 secondary ohms
\  Diameter = = 16.59 W
B. Loss of excitation setting for Diesel Engine Generator (DEG)
                       






·       Setting

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Enable Voltage Supervision
Yes
Yes
Voltage Level
0.70 x Rated
0.70 x Rated
Circle 1 Trip
Latched
Latched
Assign Circle 1 Trip Relays (1-4)
1, 2, 3
1, 2, 3
Circle 1 Diameter
15.5 Wsec
29 Wsec
Circle 1 Offset
3.7 Wsec
7 Wsec
Circle 1 Trip Delay
3s
3s
Circle 2 Trip
Latched
Latched
Assign Circle 2 Trip Relays (1-4)
1, 2, 3
1, 2, 3
Circle 2 Diameter
22.2 Wsec
42 Wsec
Circle 2 Offset
3.7 Wsec
7 Wsec
Circle 2 Trip Delay
4 s
4 s
Distance
Not applicable since it is intended for transmission line

3.1.6.3 Power Element

Reactive Power
Not necessary
Low Forward Power
Not necessary
Reverse Power Trip
·       Consideration/formula
According to ANSI Std C37-102-1987, the gas turbine prime mover usually have capability maximum motoring power up to 50% of rating and a diesel engine with no cylinder firing represented a load of up to 25% of rating, so the sensitivity is not critical.
In this project, there are two types of generator, gas turbine generator and diesel engine generator. The sensitivity of reverse power relay is not critical problem due to large power required to motor.



·       Setting

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Block Reverse Power From Online
2 s
2 s
Reverse Power Alarm
Unlatched
Unlatched
Assign Alarm Relays (2-5)
5
5
Reverse Power Alarm Level
0.04 x Rated  MW
0.04 x Rated  MW
Reverse Power Alarm Delay
25 s
20 s
Reverse Power Trip
Latched
Latched
Assign Trip Relays (1-4)
1,3
1,3
Reverse Power Trip Level
0.06 x Rated  MW
0.06 x Rated  MW
Reverse Power Trip Delay
5 s
12 s

3.1.6.4 RTD Element

Disable

3.1.6.5 Thermal Mode.

Disable

3.1.7 Setpoint / Monitoring

Trip Counter
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Trip Counter Alarm
Latched
Latched
Assign Alarm Relay (2-5)
5
5
Trip Counter Alarm Level
10 trips
10 trips
Trip Counter Alarm Event
ON
ON
Breaker Failure
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Breaker Failure Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
Breaker Failure Level
1.1 x CT
1.1 x CT
Breaker Failure Delay
80 ms
80 ms
Breaker Failure Alarm Event
ON
ON
Trip Coil Monitor
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Trip Coil Monitor Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
Supervision of Trip coil
52 Closed
52 Closed
Trip Coil Monitor Alarm Event
ON
ON
VT Fuse Failure
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
VT Fuse Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
VT Fuse Alarm Event
ON
ON
Current Demand
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Current Demand Period
15 min
15 min
Current Demand Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
Current Demand Limit
1.01 x FLA
1.01 x FLA
Current Demand Alarm Event
ON
ON
MW Demand
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
MW Demand Period
15 min
15 min
MW Demand Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
MW Demand Limit
1.01 x Rated
1.01 x Rated
MW Demand Alarm Event
ON
ON
MVAR Demand
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
MVAR Demand Period
15 min
15 min
MVAR Demand Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
MVAR Demand Limit
1.11 x Rated
1.11 x Rated
MVAR Demand Alarm Event
ON
ON
MVA Demand
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
MVA Demand Period
15 min
15 min
MVA Demand Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
MVA Demand Limit
1.1 x Rated
1.1 x Rated
MVA Demand Alarm Event
ON
ON
Pulse Output
Disable
Generator Running Hour Setup
·       Setting for All Generators

GPR for GTG
1147-GTG-600”A/B”
GPR for DEG
1147-DEG-620
Initial Gen. Running Hours
0 h
0 h
Gen. Running Hours Alarm
Unlatched
Unlatched
Assign Alarm Relay (2-5)
5
5
Gen. Running Hour Limit
1000 h
1000 h


3.2 Motor Protection

3.2.1 Largest motor at MCC “A & B”

§ 
Protective Scheme One Line Diagram
§  Protected Equipment:
The protection is intended to protect motor against overload, short-circuit and locked rotor.
·         Tag Number                  : 1130-KM-310A/B – Propane Compressor
·         Model, Manufacturer      : Squirrel cage induction motor / Toshiba
·         Rating                          : 300 HP
·         Full load CURRENT (FLA)        : 378.1Amps
·         Locked Rotor                : 6 x FLA
·         Starting Device              : Soft Starter (manufacturer: ABB)
·         Service factor                : 1.15
§  Protective device:
·         The Overload (OL) device
o    Model, Manufacturer      : CEFB1-52-120VAC, Allen Bradley
o    Rating Trip Range         : 160 – 630A


·         The motor circuit protection (MCP)
o    Manufacturer    : Merlin Gerin
o    Model              : NS630H, MA500 # 32950
o    Type                : MCCB 3P
o    Frame              : 500 Amps
o    Nominal Current, In       : 500 A
o    Trip setting, Im              : 9 – 14 x In
o    Trip Rating       : 3150 - 6250 Amps
o    Trip setting       : > locked rotor current
§  Consideration
Soft starter is equipped with MCP to against locked rotor and short circuit. Due to operation of soft starter only for starting motor and after that it will be bypassed when steady state (normal running) is achieved. Therefore, it need to added other MCP on the upstream to protect running motor.
The MCP(motor) trip setting is set 600% FLA by manufacturer and can not/forbidden be change. To prevent overlap protection, the MCP is set more than 600% FLA.
§  Setting
1.       Thermal O/L
Trip setting : 125% of FLA (according ANSI/NFPA 70 – 2002, article 430.32(1))
Þ     Trip setting = 1.25 x 378.1 Amps = 472.63 Amps, so trip setting = 480 Amps.
2.       The motor circuit protection (MCP)

Þ Im = 9 x In or equal to 4500A
§  Time Current Curves of Protection Coordination. See attachment #1


3.2.2 Largest motor at MCC “U”

§  Protective Scheme One Line Diagram

 

§  Protected Equipment:
The protection is intended to protect motor against overload, short-circuit and locked rotor.
·         Tag Number                  : 1155-PM-702 – Elec. Fire Water Pump
·         Model, Manufacturer      : Squirrel cage induction motor / US Motor
·         Rating                          : 125 HP
·         Full load Current (FLA)  : 179.4 Amps
·         Locked Rotor                : 6 x FLA
·         Starting device               : Soft starter (manufacturer: Cutler-Hammer)
·         Service factor                : 1.15
§  Protective device:
·         MCCB 3P (Thermal-Magnetic Breaker)
o    Manufacturer                : Merlin Gerin
o    Model                          : NS250H + MA220
o    Type                            : MCCB 3P
o    Frame                          : 250 Amps
o    Nominal Current, In       : 220 A
o    Trip setting, Im              : 9 – 14 x In


§  Consideration
See above paragraph.
§  Setting
1.       Thermal O/L
Trip setting : 125% of FLA (according ANSI/NFPA 70 – 2002, article 430.32(1))
Þ     Trip setting = 1.25 x 179.4 Amps = 224.3 Amps, so trip setting = 250 Amps.
2.       The motor circuit protection (MCP)

Þ Im = 9 x In or equal to 1980A
§  Time Current Curves of Protection Coordination, see attachment #2

3.3 Coordination Relay – Case #1

Overcurrent Protection Coordination for Largest Motor  at MCC “A” & Main Switchgear 
o   




Protective Scheme One Line Diagram




o    Protective device & others data:
§  Motor Protection (see paragrap 4.2.1)
§  Protective device at main switchgear outgoing feeder to MCC “A”:
¨       Feeder Name: 52-F3
¨       Manufacturer/type: Merlin Gerin/ ACB 3P – NW20H1+Microlgic 6.0A
¨       Rating: 2000AT/2000AF
¨       Nominal Current, In = 2000A
¨       Breaking Capacity (Icu) = 100 kA
§  Equipment cable:
¨       Size: 3 x 3/C # 2/0 AWG,
¨       Insulation: XLPE
§  Max. 3 phase fault at MCC “A” & Main Switchgear = 52.7 kA rms-sym, see short-circuit calculation C-1100-ELE-004.
§  Max. current flows to MCC “A” is 688A, see load flow calculation C-1100-ELE-002.
o    Setting
Feeder 52-F3, ACB 4P (NT08H1) + Micrologic 6.0A
     


Þ So setting of Ir is 0.7 x In   or equal to 1400A
This “Relay” is backup protection of downstream breaker (motor breakers) and to protect MCC “A” bus bar. Largest motors is considered due to highest current flow during starting.
Referring to coordination curve on attachment #1, setting of micrologic 6.0A is determined as follow:  
Þ Setting of tr = 6s @ 6 x Ir (8400 A)
Þ Setting of Isd = 5 x Ir (7000 A at 3 s)
Þ Setting of I2t(OFF at 10 Ir) = 0.2s (at 14000A)
Þ Setting of Ii = 15 x In (30000A at 0.05s)

Value
Ir (x In)
0.7
ts (@6Ir)
4
Isd (x Ir)
5
tsd (i2t)
0.2 OFF
Ii (In)
15
Ig
A
tg (i2t)
0.1 OFF
Þ    In = 2000A
Note: The above setting is also applied for Feeder 52-F3 (MCC “B”)


3.4 Coordination Relay – Case #2

Overcurrent Protection Coordination for Largest Motor  at MCC “U” & Main Switchgear 
o   

Protective Scheme One Line Diagram

o    Protective device & others data:
§  Motor Protection (see paragraph 4.2.2)
§  Protective device at main switchgear outgoing feeder to MCC “U”:
¨       Feeder Name: 52-F9
¨       Manufacturer/type: Merlin Gerin/ ACB 3P – NW12H1+Microlgic 6.0A
¨       Rating: 1250AT/1250AF
¨       Nominal Current, In = 1250A
¨       Breaking Capacity (Icu) = 100 kA
§  Equipment cable:
¨       Size: 2 x 3/C # 1/0 AWG,
¨       Insulation: XLPE
§  Max. 3 phase fault at MCC “U” & Main Switchgear = 52.7 kA rms-sym, see short-circuit calculation C-1100-ELE-004.
§  Max. current flows to MCC “U” is 413A, see load flow calculation C-1100-ELE-002.


o    Setting
Feeder 52-F9, ACB 4P (NT08H1) + Micrologic 6.0A
      
Þ So setting of Ir is 0.7 x In        or equal to 875A
This “Relay” is backup protection of downstream breaker (motor breakers) and to protect MCC “A” bus bar. Largest motors is considered due to highest current flow during starting.
Referring to coordination curve on attachment #2, setting of micrologic 6.0A is determined as follow:  
Þ Setting of tr = 16s @ 6 x Ir (5250 A)
Þ Setting of Isd = 4 x Ir (3500 A at 3 s)
Þ Setting of I2t(OFF at 10 Ir) = 0.1s (at 8750A)
Þ Setting of Ii = 10 x In (18750A at 0.05s)

Value
Ir (x In)
0.7
ts (@6Ir)
8
Isd (x Ir)
4
tsd (i2t)
0.2 OFF
Ii (In)
15
Ig
A
tg (i2t)
0.1 OFF
                        In = 1250A

3.5 Coordination Relay – Case #3

Overcurrent Protection Coordination for MCC “Camp” and Main Switchgear 1147-PSW2-01 
o   

Protective Scheme One Line Diagram



o    Protective device & others data:
§  Largest outgoing feeder MCC “Camp”
·         Manufacturer    : Merlin Gerin
·         Type/model      : MCCB / NS100H + TM100D (80-100)
·         Rating              : In = 100A
·         Breaking Capacity (Icu) = 70 kA
§  Protective device at incoming side of MCC “Camp”: ACB 4P (NT08H1) + Micrologic 6.0A.
¨       Manufacturer/type: Merlin Gerin/ ACB 4P – NT08H1+Microlgic 6.0A
¨       Rating: 800AT/800AF
¨       Nominal Current, In = 800A
¨       Breaking Capacity (Icu) = 65 kA
§  Protective device at outgoing feeder of Main Switchgear:
¨       Manufacturer/type: Merlin Gerin/ ACB 3P – NT08H1+Microlgic 6.0A
¨       Rating: 1250AT/1250AF
¨       Nominal Current, In = 1250A
¨       Breaking Capacity (Icu) = 100 kA
§  3 phase fault, see short-circuit calculation C-1100-ELE-004:
¨       MCC “Camp” = 6.8 kA rms-sym
¨       Main switchgear 1147-PSW2-01A = 52.7 kA rms-sym
§  Maximum current flows to MCC “Camp” is equal to full load current transformer 1163-PTR2-01 “A or B”
§  Transformer 1163-PTR2-01
¨       Manufacturer/type: Unindo/Oil Immersed
¨       Rating: 400 kVA, 400/400V, D-Y solid grounded
¨       Thermal capability curve : IEC curve
¨       Inrush Current = 5 x Inominal or 2887A, 1 second (see datasheet DS-1163-PTR2-01)
o    Setting
1.       Setting of MCCB (NS100H + TM100D)
Þ Setting of Ir = 1 x In or equal 100A
Þ Setting of Ii = 800A (fixed)
2.       Camp Incoming Feeder 52-1A, ACB 4P (NT08H1) + Micrologic 6.0A
Maximum current flows to MCC “Camp” :
       


then,
      


Þ So setting of Ir is 0.8 x In               (640A)
This “Relay” is backup protection of downstream breaker and to protect MCC bus bar. The maximum 3 phase fault is same with downstream. Referring to coordination curve on attachment #3, setting of micrologic 6.0A is determined as follow:  

Value
Ir (x In)
0.8
ts (@6Ir)
4
Isd (x Ir)
2
tsd (i2t)
0.2 OFF
Ii (In)
10
Ig
A
tg (i2t)
0.1 ON
                        In = 800A
Note: The above settings are also applied for Incoming Feeder 52-1B
3.       Main Switchgear Outgoing Feeder 52-F5, ACB 4P (NW12H1) + Micrologic 6.0A
This “Relay” is backup protection of downstream breaker and also protect cable feeder and transformer if fault occur between both breakers. Referring to coordination curve on attachment #3, setting of micrologic 6.0A is determined as follow:  
\  Setting of Ir



Þ So setting of Ir is 0.7 x In (875A)
Þ Setting of tr = 8s @ 6 x Ir (4320A)
Þ Setting of Isd = 4 x Ir (3500 A at 3)
Þ Setting of I2t(OFF at 10 Ir) = 0.1s (at 7200A)
Þ Setting of Ii = 9 x In (7200 A at 0.05s)

Value
Ir (x In)
0.7
ts (@6Ir)
10
Isd (x Ir)
4
tsd (i2t)
0.4 OFF
Ii (In)
15
Ig
A
tg (i2t)
0.1 OFF
                        In = 1250A
Þ  
Note: The above settings are also applied for Outgoing Feeder 52-F8


3.6 Coordination Relay – Case #4

Overcurrent Protection Coordination for PDB-Operation Bldg, Switchgear 1162-PSW2-01, and Main Switchgear 1147-PSW2-01
o   




Protective Scheme One Line Diagram


o    Protective device & others data:
§  Largest outgoing feeder PDB “Operation Building”
·         Manufacturer    : Merlin Gerin
·         Type/model      : MCCB / NS100H + TM100D (80-100)
·         Rating              : In = 100A
·         Breaking Capacity (Icu) = 70 kA


§  Protective device at incoming of PDB “Operation Building”:
¨       Manufacturer/type: Merlin Gerin/ MCCB 4P – NS400N+STR23SE
¨       Rating: 400AT/400AF
¨       Nominal Current, In = 400A
¨       Breaking Capacity (Icu) = 45 kA
§  Protective device at outgoing feeder of switchgear 1162-PSW2-01A:
¨       Manufacturer/type: Merlin Gerin/ ACB 4P – NT06H1+Microlgic 6.0A
¨       Rating: 400AT/400AF
¨       Nominal Current, In = 400A
¨       Breaking Capacity (Icu) = 42 kA
§  Protective device at outgoing feeder of Main Switchgear:
¨       Manufacturer/type: Merlin Gerin/ ACB 3P – NW12H1+Microlgic 6.0A
¨       Rating: 1250AT/1250AF
¨       Nominal Current, In = 1250A
¨       Breaking Capacity (Icu) = 100 kA
§  3 Phase Fault, see short-circuit calculation C-1100-ELE-004:
¨       PDB “Op. Bldg.” = 6.3 kA rms-sym
¨       Switchgear 1162-PSW2-01 = 6.7 kA rms-sym
¨       Main switchgear 1147-PSW2-01A = 52.7 kA rms-sym
§  Maximum current flows to MCC “Camp” is equal to full load current transformer 1162-PTR2-01 “A or B”
§  Transformer 1162-PTR2-01
¨       Manufacturer/type: Unindo/Oil Immersed
¨       Rating: 250 kVA, 400/400V, D-Y solid grounded
¨       Thermal capability curve : IEC curve
¨       Inrush Current = 5 x Inominal or 1805A, 1 second (see datasheet DS-1162-PTR2-01)
o    Setting
1.       Setting of MCCB (NS100H + TM100D)
Þ Setting Ir = 1 x In or equal 100A
Þ Setting Ii = 800A (fixed)
2.       Setting of MCCB (NS400N+STR23SE)
From load flow study C-1100-ELE-002, operating current flows to 1162-PDB2-01A is 81 ampere
      Ir = 2*81 = 162A
Þ Setting of long time delay,
§   Io = 0.9 x  In or equal 360A
§   Ir = 0.8 x Io or equal to 288A
Þ Setting of short time delay, Im = 5 x  Ir or equal 1440A
Þ Setting of instantaneous, Ii = 11 x In (fixed) or equal to 4400A
3.       Op. Building Incoming Feeder 52-1A, ACB 4P (NT06H1) + Micrologic 6.0A
Maximum current flows to switchgear “Op. Bldg” :
     


Þ So setting of Ir is 0.95 x In or equal to 380A
This “Relay” is backup protection of downstream breaker and also to protect switchgear bus bar. Referring to coordination curve on attachment #4, setting of micrologic 6.0A is determined as follow:

Value
Ir (x In)
0.6
ts (@6Ir)
8
Isd (x Ir)
6
tsd (i2t)
0.2 OFF
Ii (In)
10
Ig
A
tg (i2t)
0.2 OFF
                  In = 630A 
Note: The above settings are also applied for Incoming Feeder 52-1B
4.       Main Switchgear Outgoing Feeder 52-F2, ACB 3P (NW12H1) + Micrologic 6.0A
This “Relay” is backup protection of downstream breaker and also protect cable feeder and transformer if fault occur between both breakers. Referring to coordination curve on attachment #4, setting of micrologic 6.0A is determined as follow:

Value
Ir (x In)
0.6
ts (@6Ir)
12
Isd (x Ir)
5
tsd (i2t)
0.4 OFF
Ii (In)
15
Ig
A
tg (i2t)
0.1 OFF
                  In = 1000A
Note: The above settings are also applied for Outgoing Feeder 52-7


3.7 Coordination Relay – Case #5

Overcurrent Protection Coordination for Largest Outgoing (Main Switchgear) and GTG’s Breaker (Normal Operation)
o    

Protective Scheme One Line Diagram


o    Protective device, others data and setting:
§  In normal operation, largest outgoing feeder of Main Switchgear is to MCC “A/B”. Setting of the ACB, refer to paragraph 4.3 (Normal Condition – GTG’s ON)
§  Protective device at incoming of Main Switchgear: Multilin SR 489 – Over current with Voltage Restraint, see paragraph 5.1.6
§  3 Phase Fault, see short-circuit calculation C-1100-ELE-004:
¨       Main switchgear 1147-PSW2-01A = 52.7 kA rms-sym
¨       Max. fault current is supplied by GTG = 18.9 kA
o    Consideration/formula

Relay time dial setting.  Refer to ANSI extremely Inverse Curve for characteristic of the inverse time relay. Since GTG’s breaker is as backup relay, it must be coordinated with outgoing breaker(micrologic) of main switchgear. By adding a coordination time interval (CTI) 0.3s to them, the setting of Multilin O/C relay is more than 0.5s for Max. Fault Current supplied by GTG.

then from ANSI curve; it is found TMD =  4 & operating time of relay is about 1.2s at 18.9kA.
o    Setting:
See paragraph 4.1.6.1, section phase O/C (A)

3.8 Coordination Relay – Case #6

Overcurrent Protection Coordination for Largest Outgoing (Main Switchgear) and DEg’s Breaker (Emergency Operation)
o   


Protective Scheme One Line Diagram

o    Protective device, others data and setting:
§  In emergency operation, Largest outgoing feeder of Main Switchgear is to MCC “U”. Setting of this ACB, refer to paragraph 4.4 (Normal Condition – GTG’s ON)
§  Protective device at incoming of Main Switchgear: Multilin SR 489 – Over current with Voltage Restraint, see paragraph 5.1.6
§  Max. Fault, see short-circuit calculation C-1100-ELE-004:
¨       Main switchgear 1147-PSW2-01”B” = 52.7 kA rms-sym
¨       Max. fault Current is supplied by DEG = 10.8 kA
o    Consideration/formula

Relay time dial setting.  Refer to ANSI extremely Inverse Curve for characteristic of the inverse time relay. Since DEG’s breaker is as backup relay, it must be coordinated with outgoing breaker(micrologic) of main switchgear. By adding a coordination time interval (CTI) 0.3s to them, the setting of Multilin O/C relay is more than 0.5s for Max. Fault Current supplied by DEG.

then from ANSI curve; it is found TMD =  10 & operating time of relay is about 3s at 10.8kA.
o    Setting:
See paragraph 4.1.6.1, section Phase O/C (B).

3.9 Ground Fault  Relay

o    Protective device & others data:
A. at MCC “Camp”
¨       Manufacturer/type: Merlin Gerin/ ACB 4P – NT08H1+Microlgic 6.0A
¨       Rating: 800AT/800AF
¨       Nominal Current, In = 800A
B. at Switchgear “Op. Bldg”
¨       Manufacturer/type: Merlin Gerin/ ACB 4P – NT06H1+Microlgic 6.0A
¨       Rating: 400AT/400AF
¨       Nominal Current, In = 400A
o    Consideration
The purpose of this relay is not to limit fault damage of equipment but to protect human life, so that it need high sensitivity to detect ground fault.
o    Setting
A. Ground Fault Relay (Micrologic 6.0A) at MCC “Camp”
Þ Ground Fault Pickup, Ig = In x A (minimum setting A= 0.2, see attachment #3) 
Þ Time delay (ms) at In, I2t Off = 0.2
B. Ground Fault Relay (Micrologic 6.0A) at Switchgear ”Op. Bldg”
Þ Ground Fault Pickup, Ig = In x A (minimum setting A= 0.3, see attachment #3) 
Þ Time delay (ms) at In, I2t Off = 0.2




Share this Post Facebook Twitter Google+ WhatsApp

Subscribe to receive free email updates:

0 Response to "How to setting Relay Coordination"

Post a Comment

Loading...